Dunmurry tower blocks' demolition slowed due to "legal proceedings" and asbestos

An image of Rathmoyne tower in Dunmurry
-Credit: (Image: Reach Publishing Services Limited)


The NI Housing Executive has revealed how asbestos surveys and legal "proceedings" over a telecoms mast have "slowed" the demolition of two Dunmurry tower blocks.

Concerns about rough sleepers are also causing delays to the pulling down of Rathmoyne and Coolmoyne House which were cleared of all tenants in February as part of a NIHE £308m Tower Block Action Plan, aimed at replacing ageing tower blocks with new homes.

CEO of the NIHE, Grainia Long was scrutinised in Lisburn and Castlereagh City Council (LCCC) chambers last week over the demolition delay as an elected rep raised fears for homeless people sheltering in cold weather conditions.

READ MORE: Lisburn to host UK Armed Forces v Irish Defence Forces football tournament.

READ MORE: Lisburn Castlereagh taking 'legal advice' on allowing Belfast residents to use recycling centre.

Lisburn North DUP cllr, Jonathan Craig said: "I am sure you are fed up of me asking this question, but when are the two tower blocks going to come down at the front of Seymour Hill?

"It is starting to cause problems. I don't know if the Executive is aware, but there are individuals now sleeping outside those buildings in the open, homeless people, because the site isn't secured. I would hope that the NIHE would be trying to find some form of temporary accommodation for them since the temperatures are now dropping."

Ms Long responded: "Coolmoyne and Rathmoyne are both priorities for us. Both are on the future programme of schemes and we know it is a really important site.
"Anybody who physically needs our assistance, who we are not aware of, we can follow up on that."
A NIHE officer added: "As regards the two tower blocks, we are currently working on the tender document for the demolition contract. It was slowed down a little bit, because we had to carry out more asbestos surveys to inform that demolition.
"We are hoping that will go out fairly soon. And we would anticipate appointing a contractor at some time around February/March at which point we will start to take them down.
"I think it is important to realise that we probably won't be taking both down at the same time, but will be phased and it will probably be Coolmoyne first.
"The reason for that is we have a telecoms mast on Rathmoyne and we are still in legal proceedings about the removal of that mast."

For all the latest news, visit the Belfast Live homepage here and sign up to our daily newsletter here.