M56 motorway closures on Manchester Airport route begin

Work on the M56
-Credit: (Image: National Highways)


Work on one of the busiest parts of the M56 is now underway, with Manchester Airport passengers warned to leave extra time.

National Highways is resurfacing sections of worn carriageway on both the eastbound and westbound carriageways between junction 5 of Manchester Airport and junction 6 at Hale Barns in overnight work which started on Monday, June 10.

Some of the slip roads at junctions 5 and 6, as well as at junction 4 for Wythenshawe, will also be resurfaced. All the work - which also includes replacing some bridge joints and traffic detection loops in the road surface - will be done overnight with occasional carriageway or slip road closures.

READ MORE: Driver arrested as man, 35, dies after car crashes into tree

READ MORE: Police thought he was a burglar but what they found inside house was more sinister

The working hours will be between 9pm and 5am - or 7am on Saturdays. The resurfacing programme includes a full closure of the eastbound carriageway between junction 7 and junction 5, en-route to the airport, for five nights from the evening of Monday, June 17 to the morning of Saturday, June 22.

Drivers heading to the airport and beyond will be able to use an alternative motorway route using the northbound M6, eastbound M62, anti-clockwise M60 and westbound M56.

A further full closure of the eastbound carriageway, between junction 6 and junction 4, is scheduled for the nights of Tuesday and Wednesday June 11 and 12 and Monday, Tuesday and Wednesday July 8, 9 and 10. A diversion will operate from junction 6 via the local road network incorporating Runger Lane/Thorley Lane to the airport and onwards to junction 4 via the A555, Styal Road and Simonsway.

The Runger Lane/Thorley Lane diversion route to the airport will also be in place when the eastbound M56 is closed between junction 6 and junction 5 on Thursday and Friday, June 13 and 14, Monday, Tuesday and Wednesday, June 24, 25, and 26 and Thursday and Friday, July 4 and 5.

Two slip road closures affecting journeys to the airport will also be taking place:

  • Eastbound exit slip road at junction 5 on Friday, June 28 with drivers on the eastbound M56 needing to exit at junction 3a instead - joining the westbound M56, travelling back to junction 5 and using the westbound exit slip road to get to the airport.

  • Westbound exit slip road at junction 5 on Wednesday, July 17 with drivers on the westbound M56 needing to exit at junction 6 instead – joining the eastbound M56, travelling back to junction 5 and using the eastbound exit slip road to get to the airport.

National Highways project manager Rob Williams said: “This is important, if routine, wear and tear work. We are aiming to be well out of the way before the start of the school summer holiday period. We’re working closely with the airport to ensure they are aware of our timetable and a small number of overnight closures which will mean drivers needing to leave a little bit of extra time to get to work or check-in for flights.”