Stonehenge tunnel work continues despite High Court ruling plan is unlawful

Traffic passes along the busy A303 that currently runs besides the ancient neolithic monument of Stonehenge near Amesbury - Matt Cardy
Traffic passes along the busy A303 that currently runs besides the ancient neolithic monument of Stonehenge near Amesbury - Matt Cardy

Stonehenge tunnel work is to continue despite a High Court ruling that the decision to approve it is unlawful, as Highways England says it believes the road is the "best solution".

The Government-owned company has said it will proceed with handing out construction contracts for the road as a Department for Transport appeal may resurrect the project.

Archaeological fieldwork and preliminary works scheduled to start later this summer have been postponed. The Government has not yet said whether it plans to appeal against the ruling.

Grant Shapps, the Transport Secretary, gave the go-ahead to the £1.7 billion scheme to overhaul eight miles of the A303, including the construction of a two-mile tunnel passing by the prehistoric monument, in November last year.

This was despite advice from Planning Inspectorate officials that it would cause "permanent, irreversible harm" to the Unesco World Heritage Site in Wiltshire.

Save Stonehenge World Heritage Site challenged his decision in the High Court, and on Friday Mr Justice Holgate ruled it was "unlawful".

There was a "material error of law" in the decision-making process because there was no evidence of the impact on each individual asset at the historic site, Mr Justice Holgate found.

He added that Mr Shapps failed to consider alternative schemes, in accordance with the World Heritage Convention and common law.

Three bids to carry out the work have been submitted, and Highways England is expected to announce its choice of contractor early next year.

A separate £60 million contract is due to be awarded late this year for supporting the management of the construction work.

David Bullock, Highways England's project manager for the scheme, said: "We have to wait while the Department for Transport considers its options, and in the meantime we are continuing with the process to appoint a contractor for the main works phase of the scheme.

"We have now paused our plans to carry out early, preparatory work, but the procurement process is very much live to ensure we maintain programme timescales as best as possible.

"We still believe our project is the best solution to the ongoing issues along the A303 past Stonehenge.

"It has been developed after a long and extensive collaboration with our key stakeholders, and we are still very much motivated to leave a legacy beyond the road - for Stonehenge, the World Heritage Site, our local communities and future generations."