Traffic lights built as part of £3.5m scheme havn't been switched on in four YEARS

The part-time traffic lights on a roundabout in Preston, Lancs, have remained switched off since they were erected in June 2010 because congestion in the area 'hasn't been serious enough'

These traffic lights were built on a roundabout as part of a £3.5m scheme four years ago - but they still haven’t been switched on.

The part-time traffic lights, designed to tackle congestion, have remained switched off since they were erected in June 2010.

Despite the huge outlay, they’ve remained off as traffic at the roundabout in Preston, Lancs, hasn’t been serious enough to switch them on.

The lights were put in place as part of a number of traffic schemes in the area, paid for by United Utilities at a cost of about £3.5m.

They formed part of a major scheme to prevent water pollution, which was taking place at the time.

[Parking mad: UK's 'most pointless double yellow lines' are just 18 inches long]

[Top Gear fan dressed as 'The Stig' runs half marathon - stopping at every set of red traffic lights]


Paul Dunne, highways manager for Preston, Lancs., said United Utilities had paid a contribution towards future traffic management for the area at the time.

He said: 'When United Utilities were doing major works in this area, we took the opportunity to seek a contribution from them towards the future needs of traffic management in Riversway.



'One of the projects which resulted as part of a wider scheme of works to prevent congestion is the part-time traffic lights at Mariners Way.'

Mr Dunne said other improvements had thus far 'kept traffic flowing well', but as it increased, drivers would begin to benefit from congestion-busting measures.

[VIDEO: Driver fired for filming himself tailing ambulance 'as quick way to get to work']

[Mum with disabled daughter campaigns for wheelchair ramp - and gets £40,000 'slalom' eyesore]


He said: 'Improvements at other junctions made as part of this scheme have kept traffic flowing well, which mean that traffic has not yet reached the level needed to trigger the part-time lights.

'However, as this area of Preston continues to develop, weight of traffic will increase and drivers will begin to benefit from all the measures we've taken to prevent and manage congestion.'

Coun Bhilhu Patel, who represents Riversway on Preston Council, said it was 'fortunate' that some of the traffic measures had not been needed.

He said: 'Lots of money was spent by United Utilities on all junctions trying to benefit traffic flow, and the area benefitted.

'But I think we've been very fortunate that some of the systems that were created have not had to be used.'